How much does a 1000 sq ft concrete slab cost in Stillwater, OK?
| Typical total$5.74 per ft² of slab | $5,741 |
|---|---|
| Range you should see in bidsthree bids on the same scope normally land inside this | $3,533 – $9,716 |
| Labor portion50% of the job — this is the part that moves by city | $2,871 |
| Material portion50% — bought at national prices | $2,871 |
| Cement Masons and Concrete Finishers pay near StillwaterBLS does not publish a metro figure for cement masons and concrete finishers near Stillwater, OK, so this is the Oklahoma state average, SOC 47-2051 | $46,030/yr |
| U.S. mean for the same tradeSOC 47-2051 | $60,050/yr |
| Versus the national pricetrade pay here runs −23.3% against the U.S. mean | −$759 |
| Short pour season95 freezing days a year in Stillwater. ACI 306 cold-weather protection — blankets, heated water, or waiting — is a real line item here, not boilerplate | — |
Notes
- Where the number comes from. The national price for a poured concrete slab is $6.50 per ft² of slab — poured slab pricing published for 2026, $4–$11 per ft² for a 4-inch slab on grade. Labor is about 50% of that. Cement Masons and Concrete Finishers near Stillwater, OK average $46,030 a year against a U.S. mean of $60,050 — a factor of 0.767 — so the labor half is scaled by that and the material half is not. Source: BLS does not publish a metro figure for cement masons and concrete finishers near Stillwater, OK, so this is the Oklahoma state average, SOC 47-2051.
- This one falls back to a wider average. BLS did not publish a metro-level wage for this trade near Stillwater, OK, so the figure above is a state average. It is still the right order of magnitude, but a local bid carries more weight here than it would in a large metro where the survey has more responses.
- Short pour season. 95 freezing days a year in Stillwater. ACI 306 cold-weather protection — blankets, heated water, or waiting — is a real line item here, not boilerplate.
- What is in the price: excavation to grade, a compacted gravel base, forms, wire mesh or fibre, the concrete itself, placing, screeding, a broom or trowel finish, and labor.
- What is not: thickened edges for a load-bearing wall, a vapour barrier under a heated slab, rebar mats where an engineer calls for them, saw-cut control joints past the standard spacing, and any grading or drainage work around the pour. These are the lines that turn a $5,741 quote into a $7,177 invoice, so ask about each one before signing.
- Use this as a bid check, not a quote. It prices an average job in average condition. Difficult access, the state of what is being replaced, the season, and a crew booked out three months all move the real number, and none of them are in a per-unit average.
a poured concrete slab in Stillwater, OK
$5,741 is the typical number, and three bids on the same scope normally land between $3,533 and $9,716.
That is $759 less than the same job priced at the national average.
Why the city changes the number
About 50% of this job is labor — $2,871 of the $5,741 above. Labor is the only part that moves locally; a bundle of material costs what it costs wherever it is nailed down.
Cement Masons and Concrete Finishers near Stillwater average $46,030 a year, against a U.S. mean of $60,050. That is a factor of 0.767, so the labor half is scaled by it and the material half is not.
Source: BLS does not publish a metro figure for cement masons and concrete finishers near Stillwater, OK, so this is the Oklahoma state average, SOC 47-2051.
What the quote should include
Short pour season
The lines that turn a quote into an invoice
Ask about each of them before you sign. On a job this size they are the difference between $5,741 and something a quarter higher.
Use it as a bid check, not a quote
This prices an average job in average condition. Access, the state of what is being replaced, the season, and a crew booked out three months all move the real number, and none of them are in a national average.
If a bid lands outside $3,533 – $9,716, that is not automatically wrong — but it is the question worth asking out loud.
Nearby sizes
Read more
- Bags or a Truck — The Crossover Is About One Cubic YardThe arithmetic is not really about price. It is about how long a slab can sit half-poured before the joint between the halves becomes permanent.
- Concrete Slab Cost by State — 400 ft², All 51The figures price a 4-inch slab on grade. A driveway wants six inches and rebar, and that is not a small adjustment.
- Rebar in a Slab — Spacing, Cover, and Why Position Matters MoreRebar laid on the ground and left there does nothing. It has to be held up into the concrete, and that is the step that gets skipped.
- Paver Base Cost — What the Layer Nobody Sees Actually CostsThe base is a third of the material cost and all of the reason a patio either stays flat or does not.